Nebius Unveils a $40 Billion Build-Out Plan as Cracks Begin to Show

November 27, 2026
Nebius Unveils a $40 Billion Build-Out Plan as Cracks Begin to Show

On Thursday’s third-quarter earnings call, Nebius outlined plans to spend $40 billion in 2027, a figure well above what Wall Street had expected. The strategy is ambitious, but several of the projects it relies on are already running into trouble.

The company plans to finance the build-out largely through customer prepayments and loans secured by customer contracts. In effect, it is borrowing against the future income of data centers that are still being built. That approach carries real risk: if construction stalls or contracts fall through, the financing becomes much harder to sustain.

“Building at this scale is hard, and delays are part of our industry right now,” CEO Arkady Volozh said during the call. “We are not immune.”

The announcement came shortly after reports that Microsoft is growing less willing to sign neocloud deals that miss their delivery dates. That matters for Nebius, whose financing increasingly depends on repayments tied to delivery. If capacity arrives late, costs keep piling up while revenue falls behind.

Microsoft and the New Jersey delays

Microsoft is one of Nebius’s largest customers, paying for AI computing capacity at a data center in Vineland, New Jersey, that is now several months behind schedule. The Microsoft contract is worth up to $19.4 billion, yet its deadlines are already slipping. Only a little more than half of the capacity is now expected by the end of this year, with the rest pushed to the second quarter of 2027.

Nebius blames DataOne, the third-party operator of the site. According to Andrey Korolenko, Nebius’s chief product and infrastructure officer, DataOne shut down its temporary power generation sooner than expected as the facility switches to Bloom Energy fuel cells.

That switch was not entirely by choice. In August, the investigative outlet Floodlight found at least 45 natural gas generators running at the DataOne site without the permits needed to operate them. New Jersey regulators responded with a $1.1 million fine, ruling that the generators violated federal law. The facility also faces a lawsuit from nearby residents, who say a constant humming noise from the site is a nuisance.

According to Nebius’s summary of the Microsoft contract, Microsoft can terminate the affected service after a grace period if deadlines are missed and no alternative capacity is offered. The capacity was originally meant to be delivered in 2025 and 2026, so the new target of the second quarter of 2027 falls well outside that window. The contract also includes financial penalties for late delivery.

Nebius says Microsoft “has been part of the planning process,” but it has not said whether Microsoft accepted the revised timeline. Microsoft has not publicly canceled anything.

Signs Microsoft is pulling back

On the call, chief revenue officer Marc Boroditsky said both the Microsoft and Meta deals came with substantial prepayments, received long before delivery. However, Bloomberg reported last week that Microsoft is tightening oversight of projects run by third parties, including Nebius, IREN, and Nscale, and is debating whether new agreements are worth signing. Bloomberg also reported that Microsoft sent employees to the New Jersey site.

Microsoft’s own quarterly report noted that its capital spending came in below expectations because of third-party delays. Bloomberg has further reported that Microsoft will not exercise an option to more than double its Nscale agreement for a Texas data center, and that it has stopped serving as an anchor customer for Nscale’s planned Essex site after power delays.

Nebius insists the delays stem from sites it does not control, while the data centers it builds itself are on time or ahead of schedule. Those facilities, the company says, will provide most of its new capacity starting in 2027. Boroditsky added that prepayments on deals signed in the third quarter more than cover the cost of the capacity behind them. Nebius ended the quarter with $7.4 billion in cash.

Financing and forecasts

Nebius expects prepayments and asset-backed financing on investment-grade contracts to cover up to 85% of its projected $40 to $45 billion in 2027 capital spending. CFO Maria Del Dado Alonso Sanchez named Microsoft and Meta as contracts that can be financed this way. Boroditsky also said the company could “tap prepayments to shore up any additional cash requirements.”

For 2027, Nebius forecasts revenue of $12 billion to $13 billion and expects to reach break-even on a pre-tax basis by the fourth quarter.

Third-quarter revenue came in at $981 million, up 571% from a year earlier. About a third of that total came from a one-time payment tied to a new partnership model. Nebius also cut its 2026 revenue forecast by $200 million, to $3 billion, citing delays at third-party sites such as the one in New Jersey. Shares closed the day down 17%.